INDUSTRIAL: Rethinking Project Management

How to know when it’s time to upgrade from a patchwork of manual tracking tools to a disciplined, digital backbone.

Project management systems are becoming mission-critical infrastructure for industrial sheet metal and HVAC contractors because the complexity, risk and speed of today’s work have outgrown spreadsheets and paper.

When does manual job tracking become a liability? When costs and quality problems escalate, meetings expose problems, and claims and change orders rise. 

Unfortunately, construction has historically lagged other industries in digital adoption, with a significant share of contractors still relying on spreadsheets, whiteboards and paper-based workflows for planning and tracking. But adoption is accelerating under pressure from tighter margins, more complex projects and workforce shortages.

Graham Corsar, who was previously a Project Manager but now works with contractors as an Account Executive at Trimble Inc., a construction technology company, argues that the real question isn’t whether you “need a project management tool,” but whether your existing system can survive as industrial work continues advancing.

One Mistake Could Eliminate 

Your Profit Margin 
On a multi-million-dollar industrial job, an HVAC or sheet metal contractor is often living on a 5% to 10% margin, where $50,000 to $100,000 can vanish with one mistake: one missed change order, one shop error, a misread spec, late material or a crew installing from the wrong drawing.

Industrial work magnifies that risk. Large air handlers, extensive duct runs, specialty metals and complex supports mean material is a major cost driver, and much of it is ordered early, long before the last RFI is resolved. Add in aggressive schedules, tightly sequenced trades and code inspections that can shut down a floor, and a contractor’s financial outcome is inseparable from how projects are planned, tracked and documented day to day.

For many industrial shops, the system is a patchwork: estimating software feeding into Excel, hand-marked shop tickets, email chains and shared drives. “Your company already is the project management system,” Corsar argues.

Corsar breaks that system into three elements — people, processes and tools — and insists that software sits firmly in last place.

  • People: project managers, coordinators, detailers, foremen, fabricators and their experience, judgment and willingness to communicate bad news early.

  • Processes: how change orders are captured, how RFIs are logged and answered, how drawings are issued and superseded, how labor is tracked and compared against budget.

  • Tools: the actual platforms that hold drawings, budgets, time sheets, RFIs, submittals and photos.

“A new platform that just recreates the same bad habits in the cloud will not save a single dollar of margin,” he insists.

When Manual Tracking Becomes a Liability
The contractors who most urgently need a structured project management system often have the most reason to believe they can get by without one. The crews are seasoned, the estimator knows the market and the shop has its own rhythm. But Corsar asks them to look for three warning signs that show they can no longer operate without a better system:

  • Too many surprises. Costs, quality problems, schedule slips or scope gaps keep blindsiding the project team. This equates to project managers being surprised more than once a week, executives more than once a month and ownership more than once a quarter, Corsar says, signaling that the system isn’t surfacing risk early enough.

  • Progress reports that require a meeting. In many sheet metal shops, job status still comes together in a monthly ritual: someone gathers timecards, pulls the latest PO log, requests updated fabrication status, hunts through email for change approvals and then walks it all into a conference room. If there are no automated reports or dashboards, you are using meetings “to find out about problems, not to solve them,” Corsar says. 

  • Claims and change orders that leak value. If the value of missed or incomplete claims is more than 25% of your margin or if no one can say how much is missing, the contractor is effectively donating profit to the general contractor or owner. In industrial HVAC work, where scope creep often hides in “small” extra runs or rework tied to other trades, that leakage can define an entire year’s results.

When all three indicators show up on the same jobs, Corsar says the problem is not “bad luck;” it is the project management system itself, and spreadsheets are part of the problem.

Who Actually Needs Project Management Software?
Corsar doesn’t pretend every contractor needs a heavyweight project management platform tomorrow. Instead, he challenges firms to ask what they are really trying to fix and to focus first on process. 

An integrated project management system can force changes through one documented path: an RFI or change request is logged, the model or drawing is updated, the shop status is changed, new assemblies are tagged and the cost and schedule impact are attached to that specific event. That is how a contractor turns what used to be unbilled chaos into a billable, defensible change.

For very small shops — fewer than 10 people — the question is stability. If jobs are small, scopes simple and changes rare, a modest digital backbone paired with disciplined processes may be enough. But if even one or two industrial scale jobs a year can push the company to the edge with complex coordination, multiple vendors and long lead times, that is a sign that more structured project management is no longer optional; it is insurance.

For mid-sized contractors — those with multiple foremen, a dedicated project manager or two and a real backlog — the tipping points are usually:

  • Repeated disputes over extra work, especially when documentation lives in texts and unsaved photos.
  • Chronic re entry of data from field to office — time sheets, quantities, change logs — that burns out staff and still produces inconsistent numbers.
  • Difficulty answering basic questions in real time: Where is this job versus budget? Which change orders are approved? How much labor have we really spent on this level?

For larger firms, Corsar argues, the question is not, “Do we need a project management system?” but “Is the one we have working like it should?” Overhead (office salaries, software, infrastructure and the unplanned costs of rework and missed claims) is already functioning as project management spend; the only choice is whether that spend produces visibility and control or just more noise.

How to Decide on Project Management System Software
When a contractor decides that “something has to change,” Corsar’s advice is to focus on four areas to keep the project management software decision grounded.  

  1. Budget. This means understanding not just license fees, but what you already spend on people who are doing manual project management: tracking hours, copying data, chasing signatures, reentering quantities and fixing billing errors. That cost often dwarfs the software line item.

  2. Authority. Who really decides what project management tool can work best for the company? For a sheet metal contractor, that may mean bringing in the shop superintendent and the most skeptical field foreman before any contract is signed.

  3. Need. Are you shopping for cost control, productivity, decision speed or risk management? If the “need cannot be explained in a single sentence that makes sense to the ultimate decision maker,” he warns, “you probably aren’t clear on what you’re buying.”

  4. Timing. “System change takes 12 to 24 months,” Corsar says, and contractors should not let anyone convince them it can be done faster. For industrial HVAC and sheet metal shops juggling live jobs, that means planning a rollout that respects bid seasons, shutdown windows and critical project milestones.

Processes First, Tools Second
Corsar’s most practical advice to industrial contractors is also the least glamorous: fix your processes before you pick your platform. He stresses that “good process can make up for shortcomings in tools & people,” and warns, “if you don’t have good processes, stop” before you sign any software contract.

That might mean standardizing how markups become formal change orders with a clear path from foreman sketch to priced, approved scope. It might also mean defining a single source of truth for drawings and models, so no crew is ever building off an obsolete PDF taped to a gang box. And it could even mean setting a consistent way to tie labor and material codes back to estimating templates, so job cost feedback improves future bids.

Only once those processes are clear does the choice of tool become meaningful. Industrial HVAC and sheet metal contractors do not need “another project management tool” so much as they need a system that lets their people see risk early, defend their work and protect the thin slice of margin that keeps the shop lights on. As Corsar says, “The software is only the part you can install; the rest is the company you are willing to change.” 


Published: March 6, 2026

IN THIS ISSUE


Architectural: How Automation is Reshaping Metalcraft

As robotic welders take their place beside skilled craftsmen, Poynter shows how automation is not erasing the human touch. Instead, it’s amplifying it, redefining what’s possible in modern architectural metalwork.


Government and Public AffairsIssues Update

Last year, the Government Affairs Department quietly but effectively worked diligently to produce significant legislative victories on behalf of SMACNA members.


How Contractors Can Avoid Three Common Mistakes During Periods of Growth

Periods of growth are exciting for any contractor, indicating strong demand and the opportunity to expand into new markets, larger projects or project types.


HVAC: Rewiring the Legacy

How a third-generation contractor is blending craftsmanship and code to keep Western Sheet Metal competitive in an industry racing toward automation.


INDUSTRIAL: Rethinking Project Management

How to know when it’s time to upgrade from a patchwork of manual tracking tools to a disciplined, digital backbone.


Ins and Outs of Automation

As we kick off 2026, AI and automation continue to be hot topics across many industries, and construction is no exception.


LAX’s Modular Marvel Takes Flight

Imagine nine massive concourse modules, each the size of a football field, creeping across Los Angeles International Airport’s tarmac at dawn, like gigantic puzzle pieces sliding into place.


Meet SMACNA’s New President Todd Hill

Ventcon’s innovator leads SMACNA in 2026. In the humming workshops of Troy, Michigan, where sheet metal bends to the will of skilled hands, Todd Hill has forged an impressive career.


Ninth Circuit Clarifies the Scope of the “Building and Construction Industry” Exemption for Withdrawal Liability

On Jan. 5, the U.S. Court of Appeals for the Ninth Circuit issued a decision relevant to union contractors.


PDX Terminal Expansion Brings Forest Canopy Over Concourses

Picture walking through Portland International Airport’s expanded main terminal, dappled light filtering through a 9-acre mass timber roof onto a grove of live trees below just like a Pacific Northwest forest sprouting right over security checkpoints.


Renaissance in the Steel City: PIT’s HVAC Revival

Imagine stepping into Pittsburgh International Airport’s (PIT) reborn terminal, where the ghost of its 1990s “airport of the future” glory hums anew, minus the unused gates and empty shops but brimming with streamlined efficiency.


RESIDENTIAL: Boost Your Residential HVAC Business with Social Media

Unlock the power of social media with practical strategies designed to grow your business, deepen customer relationships and stand out in a competitive market.


Strengthening Labor Harmony and Industry Bonds

I'm honored to serve as CEO of SMACNA, stepping forward at a pivotal time for our 3,500 member firms and the sheet metal, HVAC and fabrication sectors we represent.


TESTING ADJUSTING AND BALANCING: Certifying Medical-Grade HVACPerformance in a New Hospital Tower

SMACNA TAB contractor Northstar Environmental is ensuring that the HVAC system at a soon-to-open Pittsburgh hospital expansion meets the facility’s stringent expectations.


The Connector: How Frank Wall’s collaborative vision is shaping SMACNA’s next era.

When Frank Wall steps into a room, he carries more than four decades of industry experience.


The Infrastructure Work Pipeline

How transportation policy can become real work for HVAC and sheet metal contractors.


Welcome New SMACNA Members
Where Craft Meets Character

B.J. Giri never chased the spotlight. Instead, the 2025 SMACNA Contractor of the Year built a career and a company by listening first, mentoring deeply and proving that leadership in the trades is as much about people as it is about precision.